The Coe and Bradley Bridge Replacement Project gets a Green Light - It has been completed
Current Status: This project is complete and was the initial major component project of the Flood Control Implementation Agency...on time and within budget!
Recent History: The cost for the project was approximately $2 million with 80% Federal and 20% City share in the project. It was about a 2 year project.
Background: The Coe Avenue and Bradley Avenue project began with property acquisitions. They were designed to accomodate at least a 100 year storm which is a storm not likely to occur once in 100 years. The work added extra capacity to Coe Avenue Bridge and created a new bridge at Bradley Avenue.